AWE Burghfield Shortfalls – Hansard, 15th January 2008

15 Jan 2008
AWE Burghfield
Mr. Hancock: To ask the Secretary of State for Defence pursuant to the answer of 17 December 2007, Official Report, column 1035W, on AWE Burghfield, how many safety shortfalls (a) were identified by the Nuclear Installations Inspectorate (NII) during the risk assessment, (b) were resolved by the delayed 27 September 2007 target date, (c) will shortly be resolved and (d) will remain unresolved under the current single operation licensing regime imposed by the NII for each warhead handling operation; and if he will make a statement. [177368]
Mr. Bob Ainsworth: As I indicated in my answer to the hon. Member on 7 January 2008, Official Report, column 28W, the safety case issues in question were identified not by the Nuclear Installations Inspectorate (NII), but by AWE plc in its own Periodic Review of Safety. A total of 1,000 safety shortfalls were identified and these ultimately translated into 337 improvement packages requiring further action. Of these improvement

Column 1132W
packages, 234 were completed by 27 September 2007 with a further 50 due to be completed by 31 March 2008. The remaining 53 improvement packages are due to be completed by 31 December 2008.
It is important to note that NII has made a full assessment of AWE's Periodic Review of Safety and is satisfied that appropriate progress is being made at AWE Burghfield to address the findings. It is emphasised that, if NII believed a particular operation were unsafe, it would not allow it to take place, and has appropriate regulatory powers at its disposal to cease operations.

By continuing to use the site, you agree to the use of cookies. More information

The cookie settings on this website are set to "allow cookies" to give you the best browsing experience possible. If you continue to use this website without changing your cookie settings or you click "Accept" below then you are consenting to this.

Close