Nuclear Installations Inspectorate (NII)feedback to AWE Aldermaston emergency exercise May 1998

In response to FOI request by Rob Evans, Defence Procurement Agency provided AWE’s answer to the MoD question regarding NII feedback to the Aldermaston site emergency exercise at 13 May 1998. The performance of the situations control centre, health physics assessment room were deem to be good. Overall assessment of medical aspect was satisfactory. Emergency control point arrangements need to be fundamentally re-examined. Recommendations were made regarding on and off site activities and local response by facility and shift engineers.